Water

 

Now I see! TM
Fire-Safety
Econ 101
Econ201
Restoration

Case Studies
Restoring Lincoln Center

 

 

 

 

Restoring Lincoln Center

 

Analyze
Dimensionmate utilized the special research report prepared by Building Research Institute of Montana. The owner's ideas and criteria were incorporated into the analysis and the scope of work was agreed upon. The owner rejected the idea of a new roof and gutter called for by the research report because of a limited budget.

Design

The copper flashing details for this unique job were designed following the guidelines from the Copper in Architecture Handbook; Copper Development Association. Hand sketches quickly illustrated the many complex shapes required for a watertight installation.

It was determined the budget would not allow the entire masonry surface to be restored. To honor the budget and still get the job done a strategy was devised on what was to be done and how it was to be bid.

To repoint the brick and limestone and replace spalled and broken brick, areas that were most critical were estimated and included in the documents to allow all bidders an absolute quantity to bid on.

A contingency was included in the budget to allow for additional work, during the course of the project, in case the architect and the mason discovered it to be necessary. Unit prices asked for on the proposal form were used to avoid arguments.

All masonry areas were slated for cleaning but the bidding documents stated exactly how to clean the brick and limestone and how much cleaning was to be done. The contractors were told they were not responsible for removing all stubborn stains if they followed the procedures outlined in the bid documents.

Specifying cleaning this way alleviates a burden on the contractor. They do not have to go over the masonry time and time again to "make it right".

If responsibility for removing every stain falls on the contractor, they will have to pad their bid to make sure their labor, materials and equipment are covered. The owner in this case simply did not have the budget to make this requirement and expect the price to come in low.

The owner opted to make it acceptable - not perfect. In some areas the stubborn stains were not removed completely but this was viewed as a good compromise rather than the alternative of not doing the project at all.

Document

Computerized specifications using Speclink. Always up to date and maintained by professional specifications experts and edited by experienced architects.

Computerized photo-drawings with Microsoft Powerpoint are quick and compatible with most districts' electronic files. Keynotes allow changes quickly without major revisions to documents.

Hand sketches for copper details are quick, inexpensive and informative allowing the project to be bid without guesswork. The hand sketches originally done during design were used to prepare the construction documents with minor additions. This saves time and money.

Administer

Worked with general contractor reviewing a list of acceptable substitute brick masons when the original bidding mason declined to accept the job after the bid. Worked closely with new mason. Outer wythe of west wall had to be partially taken down. After loose stucco was removed it was determined the mortar was too deteriorated.

The mason elected to clean the face brick taken down from this wall and use them for the replacement brick on the other elevations. If this brick had not been available, new modular brick that wouldn't match in size or color would have been used. This area of west wall was replaced with new modular brick and stucco.


Photo of South Elevation of Lincoln Center after restoration.

Questions, Answers, and Lessons to be Learned

Q: Why did the original mason back out of the bid?

A: There is a shortage of qualified masons in this area and a mini building boom going on with many large masonry projects. These projects quickly use up all the commercial masons experienced in this type of restoration. The general contractor asked a residential mason to bid who had never done this type of work. He quickly learned it was a very difficult project; high in the air at a very busy downtown street with little room to maneuver and a limited staging area.

Example: A 110-foot manlift was at its maximum extension trying to reach the farthest corners.

Lesson: Pre-qualify bidders. Do this well before they are needed. Do not wait for emergencies to take care of restoration work that could be done more easily and with less expense if planned for in advance.

Q: Why was the stucco applied to the new modular brick on the west wall?

A: Only half of the west wall was torn down and rebuilt. The rest of the wall still had stucco that was very difficult to remove. The budget did not allow the removal of all the stucco, just the loose material. To stay within our budget there was no choice but to prepare a solid substrate and apply stucco again to the same area.

Lesson: Do not apply stucco or paint (or steel siding for that matter) to brick that need restoration. It traps moisture in the masonry assembly and accelerates the deterioration process. It compounds the problems for the future restoration of the building and increases costs.

To Learn More

Read/Contact
Masonry Design and Detailing, Christine Beall, McGraw-Hill 1987
Copper Development Association
Brick Institute of America
Indiana Limestone Institute
Building Research Institute of Montana

.

 

 

Architecture  Building Research  Wellness Center
    Transform your life, business and community.